The hunt for elusive Teetee Arrows - TTROs - goes on. When and where will our roads be closed and to what purpose? I don't remember this one (below) being issued on 9 July and I have only became aware  of it becaus  the date has changed. It will means  big doversuion but bnot as bad as when Marston Hill is shut. And assuming they achieve what they are setting out to achieve - "flood alleviation". That has to be in a good cause.

PLERASE NOTE THE CLOSURE DATE IS NOW 27th NOVEMBER to 4th DECEMBER 2013.

-->
Proposed Temporary Road Closure – Crawley Road, Cranfield

I have a request for a Temporary Road Closure at the above location to enable flood alleviation works to be carried out in safely. Details are listed in the schedule below and having assessed the application I am satisfied the request is justified.

The alternative route available for this closure is as in the details below and will be signed accordingly. The restrictions are to be in operation only when the necessary signs are erected on site. This notice will cover a four month period. Access may be allowed from time to time according to local signing.
If you have any observations you wish to make I would be grateful if you could let me know as soon as possible.
Gareth Hughes. Streetworks Co-ordinator
……………………………………………………………………………………
                       
Road:                       Crawley Road, Cranfield

Application from:   Anglian Water – 01733414396 - Emmanuel Iwuamadi

Reason:                   Flood Alleviation Scheme

Length affected:     From number 44 to 50m south of pump house

Date: The closure is expected to take place from Monday 14th October to Monday 21st October 2013 for 24 hours daily during this period. Access may be allowed from time to time according to local signing.
Alternative Route: Proceed along Crawley Road in a northerly direction and turn left onto College Road continuing into University Way, at the first roundabout take the second turn right to remain on University Way and the first exit at the second roundabout, at the third take the first turn left onto Moulsoe Road. Turn left onto High Street and continue ahead into Bedford Road, turn left onto Crane Way, at the junction turn right onto Broad Green and continue into Crawley Road to reach site and vice versa.