Further tabular info on road closures this month and into October for traffic calming works


Amey writes:





"There are not intended to be any temporary traffic signals or road closures left on overnight or over any weekend (except for Bourne End Road), though there may need to be cones and signs to protect the works.

"It is intended to complete each section before moving on to the next to minimise disruption. The programme will be monitored and should the need arise could possibly be altered to take account of any local or unforeseen issues that may arise. There can also be flexibility actual dates given to take account of actual progress - we may be able to complete some sections quicker than expected and be in a position to move on to the next section early – leading to less overall disruption. 

"Regular updates will be sent out to keep you up to date with progress and any alterations that may occur in the overall programme. Also the Advanced Warning signs warning of the traffic management can be revised if required so that the public can also be aware of any changes to the times and dates of expected disruption."




ection
Location of works
Expected Duration of works
Date/Duration of temporary traffic signals
Date/Duration of road closures
1
Crane Way/ Bedford Road
30th July to 9thAug
3 way lights 6 days (8am-6pm)
3 day closure (Tuesday 7th  – Thursday 9th: 9am-3.30pm)
2
Mill Road/ Crane Way
9th to 24th Aug
3 way lights 2 weeks (8am-6pm)
3 day closure. (Tuesday 21st – Thursday 23rd: 9am-3.30pm)
3
High street (War Memorial)
27th Aug to 13th Sept
2 way lights for 11 days (8am-6pm).
3 day closure. (Tuesday 11th – Thursday 13th: 9am-3.30pm) Localised closure to merchant lane and Court Road
4
Crawley Road
17th to 20thSept

3 day off peak closure (9am – 3.30pm)
5
Mill Road/ High Street
24th Sept to 8thOct
2 way lights for 2 weeks (8am-6pm)
3 day closure (Tuesday 18th – Thursday 20th: 9am- 3.30pm). Mill Road to be closed for 3 weeks (at the High Street).
6
High street (Cross Keys)
9th - 11th Oct

3 day off peak closure (Tuesday 9th – Thursday 11th: 9am- 3.30pm).

-
Bourne End Road (junction Broad Green)
Duration of works

Closed for use as site compound and welfare unit.