Wednesday 25 May 2011

Latest delays


This is Nick's response: 


As you know we had a delay before the trigger point for the S106 was confirmed by CBC colleagues then another delay whilst the payment was requested and subsequently received before CBC could issue us with the instruction to proceed in March 2011.

This scheme had therefore to be reprogrammed into the current financial year. We do need to verify health and safety information that was obtained for this scheme because it is time limited and this is being done. The project can then proceed to the statutory public consultation phase but you do all need to be aware that there is an opportunity there for objections to be made to any of the elements of the scheme by the public.

No comments: