I attended the stakeholder meeting on Thursday evening. 

The main headlines are:
Reserved matters have all been issued but some pre-commencement conditions are still outstanding. Persimmon are gearing up for a start. There has been no resolution between Denison and Persimmon. 


I checked that there is still the flexibility on a hall spec and Martin Wright confirmed this. He also insisted that the plans gave  an inaccurate view of how tall the building actually was. 

I queried how development could go ahead without clearance on access to Court Road. Hannah Pattinson said a Section 38 (with timetable) had to be in place but the access not actually constructed. I have to say this is an ambiguity  that needs probing.

S278 works: Paul Stone from Persimmon said he felt the roundabout issue could be resolved quickly. Following the resurfacing of Lodge Road an application would be made to do the roundabout. 

Persimmon were also probed on whether the new lay out for the access to Lodge Road was enforcing the No Left Turn requirement. There was no clear outcome on this. 